new scheduler modes in latest firmware details
Posted: Sat Oct 25, 2025 5:23 pm
						
						Details of new scheduler mode options in the latest firmware:
They've basically added battery control only or inverter output control, battery + pv control between the new modes.
ForceCharge(BAT)
——Work mode: ForceCharge. The inverter will control the power charge into battery. For example if you set the power to be 10kW that means the maximum power input to the battery is 10 kW. This is to control the input of the battery.
ForceDischarge(AC)
——Work mode: ForceDischarge. The inverter will control the power feed into grid. For example if you set the power to be 10kW that means the maximun power feed into the grid is 10kW(battery power+PV). This is to control the output of the inverter.
ForceDischarge(BAT)
——Work mode: ForceDischarge. The inverter will control the output power of battery. For example if you set the power to be 10kW that means the maximum output power of battery is 10kW. This is to control the output of the battery.
ForceCharge(AC)
——Work mode: ForceCharge. The inverter will control input power from grid. For example if you set the power to be 10kW that means the maximun power input from the grid is 10kW. At this time if there is surplus PV power it will not feed into grid. This is to control the input power from grid.
					They've basically added battery control only or inverter output control, battery + pv control between the new modes.
ForceCharge(BAT)
——Work mode: ForceCharge. The inverter will control the power charge into battery. For example if you set the power to be 10kW that means the maximum power input to the battery is 10 kW. This is to control the input of the battery.
ForceDischarge(AC)
——Work mode: ForceDischarge. The inverter will control the power feed into grid. For example if you set the power to be 10kW that means the maximun power feed into the grid is 10kW(battery power+PV). This is to control the output of the inverter.
ForceDischarge(BAT)
——Work mode: ForceDischarge. The inverter will control the output power of battery. For example if you set the power to be 10kW that means the maximum output power of battery is 10kW. This is to control the output of the battery.
ForceCharge(AC)
——Work mode: ForceCharge. The inverter will control input power from grid. For example if you set the power to be 10kW that means the maximun power input from the grid is 10kW. At this time if there is surplus PV power it will not feed into grid. This is to control the input power from grid.