H3 inverters Meter2 for monitoring third party grid tied inverter.

Posted: Sat Jan 14, 2023 4:38 pm
by mattias.lindahl
Can anyone tell how Meter2 should be installed on a H3 3 phase hybrid inverter?

We have Meter1 enabled on modbus address 001 and everything is working just fine but in the house we also have a SolarEdge inverter that I want to “see” in the FoxCloud portal as the second inverter.

This must be possible as it is on the 1 phase models? There you use CT2 clamps directly connected to a terminal but with H3 models we only use modbus.